  • Site Clearing and Earthwork: May 2018
  • Foundations: June 2018
  • Steel Erection: August 2018
  • Parking Garage: October 2018
  • Project Completion: February 2020

Project Participation Requirements

  • 20% MBE Contractors
  • 5% WBE Contractors
  • 40% Overall Diversity Goal (MBE, WBE, DBE)
  • 75% Louisville MSA Resident Workforce

Participation Goals Progress

Watch for Progress Reports to be posted here.

BID PACKAGE INFORMATION
  • Bid Package

    DR-2 Foundations

    Multiple Building Trades

    Parking Garage

  • Release Date

    May 24, 2018

    July 3, 2018

    August 8, 2018

  • Prequalification Closing

    May 1, 2018

    June 25, 2018

    August 1, 2018

  • Bid Date

    June 7, 2018

    TBD

    TBD

Request for Prequalification

View Prequalification Letter
Download Prequalification Packet

Please send the completed prequalification packet to PMCH by either email or mail. 

Email: dboien@pmchconstructors.com

Mail: 1415 Bardstown Road #8, Louisville, KY 40204

Request for MBE/WBE Information

Bid Package Awards

Awarded Companies to be Announced Soon

JOB SUPPORT & BUSINESS PARTNERS
Training
LUL-logo-short
youth-build
Screen Shot 2018-04-17 at 8.47.09 AM
Job Opportunities

Seeking Workers

Seeking Employment

Job Support or Bank/Financial Inquiries

Business Financing
1506895193_republic-bank-trust
img_logo
Business Insurance and Bonding
Screen Shot 2018-04-17 at 4.29.58 PM
PROJECT NEWS
Community Outreach Events
Diversity & Inclusion Outreach Event
Job Fairs

Check here for dates and times of job fairs for this construction project.

More Information
wellbeing-campus-logo-color
Team
Screen Shot 2018-04-17 at 9.41.02 AM
TKT Logo - Vector copy